Monday, June 3, 2024
Sound Energy announced the mobilization of the Star Valley Rig 101 to the Tendrara Production Concession in Morocco to conduct planned work over operations on the gas wells TE-6 and TE-7 in preparation for long term gas production into the micro LNG plant currently under construction at site by Italfluid Geoenergy S.r.l..
In December 2023, the company successfully completed the preparatory work over operations by installing production packers in both wells with a wireline unit. The currently planned work over operations will comprise pulling the existing completion tubing and running new corrosion resistant completion tubing utilizing the Star Valley Rig 101 which is expected to arrive on site the first week of June 2024. In addition, the existing TE-6 and TE-7 Christmas trees will be replaced with replacements containing the necessary corrosion resistant components.